RFP Section C · Work Schedule · about four months from notice to proceed

Sixteen weeks from kickoff to final report

The RFP expects the study to finish about four months after Council approval, scheduled for December 14, 2026. Our dates assume a notice to proceed on Monday, January 4, 2027. If the start moves, every date moves with it, day for day.

Jan 4
2027 notice to proceed (assumed); kickoff that week
Jan 25
On-site week in Atwater: interviews with the City Manager, HR and department heads
Mar 26
Draft findings to the City Manager and HR
Apr 23
Final report, tables and workbooks delivered
May
City Council presentation, on the agenda date the City sets

Phase 1 · Start-up and data

Mon Jan 4 to Fri Jan 22, 2027
Kickoff with the City Manager and Human Resources

Confirm goals, the study's pay philosophy questions, communication plan, the meeting calendar and who signs off at each step. Agree how employees hear about the study and when.

Deliverable: project charter and calendar (scope K)
Data request and intake

Class specifications, the incumbent file (class, step, hire and class dates, FTE), the three MOUs and side letters, benefit plan summaries and rates, CalPERS valuation reports, premium pay rosters, turnover and vacancy history. We validate the incumbent file against Salary Schedule A-27 before anything else uses it.

Deliverable: validated data set and an exceptions list for HR
Comparator agencies agreed

We bring a proposed list with the rationale written down (population, distance, services, structure, the labor market Atwater hires from, and whether the agency runs its own police and fire). The City approves it. Scope B.1 and B.2.

Deliverable: comparator memo, City-approved by Jan 22

Phase 2 · Field work and surveys

Mon Jan 25 to Fri Feb 26, 2027
Stakeholder interviews, on site

The week of January 25 in Atwater: the City Manager, Human Resources, each department head, and the bargaining representatives if the City wishes. Employee focus groups or a short online survey run the same week if the City asks for them (scope G.2).

Deliverable: interview summary, themes by department
Classification review

Every class specification read against current duties as described in the interviews and by HR. We flag specs that no longer describe the work, classes whose relationships look wrong, and series that need a level added or removed. Scope A.

Deliverable: classification findings and flag list
Salary and total compensation survey

Published salary schedules first (much of that file exists already, see the peer market page), then a short survey to each comparator for what schedules leave out: benefit premiums and caps, CalPERS formulas and cost sharing, leave, deferred compensation match, and premium pays. Scope C and E.

Deliverable: market data workbook with a source and date on every number

Phase 3 · Analysis

Mon Mar 1 to Fri Mar 26, 2027
Market position and recommended ranges

Each class placed below, at or above market on base pay and on total compensation. Recommended ranges built from market data, class responsibilities and internal relationships, with the method stated. Scope C.3 and D.

Internal equity, compression and recruitment and retention

Supervisor and subordinate gaps, entry to journey to senior steps, and the director tier, checked against the recommended structure. Turnover, vacancy and time-to-fill data read alongside the market results to find the classes where pay is driving losses. Scope F and H.

Fiscal impact and implementation options

Cost of every recommendation by class and by fund, with salary-driven benefit costs (CalPERS, Medicare, deferred compensation) included. Employees below a new minimum, inside the range, or above a new maximum each get a stated treatment. Phased options where the full cost is more than one budget year can carry. Scope I.

Deliverable: draft findings to the City Manager and HR, Fri Mar 26

Phase 4 · Review, report and Council

Mon Mar 29 to Fri Apr 23, 2027, then Council in May
City review meeting

We walk the City Manager, HR and Finance through the draft, number by number. Changes are logged with their reason.

Final report and tools

Executive summary, methodology, comparator rationale, salary and total compensation tables for every class, internal equity findings, the implementation matrix, and the electronic workbooks with formulas intact. A maintenance guide so HR can age the market data and place new hires consistently between studies. Scope J and objective 7.

Deliverable: final report, Fri Apr 23
City Council presentation

Presented in person by the project manager, on the Council agenda date the City sets (we expect a regular meeting in May 2027). Scope K.

How we keep the dates

Status goes to HR in writing every other week, with the next two weeks' asks named. The comparator list and the data request close in the first three weeks because every later step depends on them. The draft goes out a month before the final so the City has time to read it. The one risk to the schedule we cannot control is data arriving late; we name that risk at kickoff and track it in every status note.